construction planning - photo courtesy of Indypendenz on shutterstock
construction planning - photo courtesy of Indypendenz on shutterstock

Caltrans will later Friday continue lane reduction and demolition work along the southbound San Gabriel River (605) Freeway in Whittier, authorities said.

The demolition will occur on the southbound 605 Freeway, from southbound Pomona (60) Freeway to Peck Road, said Caltrans spokesperson Marc Bischoff.

“Residents and businesses located in this area may experience noise, vibrations and dust associated with demolition activities,” Bischoff said. “All closures are subject to change. Ramp traffic will be detoured via local arterial routes during the hours of the ramp closures.”

There will be no full freeway closures associated with the operation, he said.

Freeway Lanes:

— Southbound I-605 reduced to three lanes from 8 p.m. to 9 p.m. Friday.

— Southbound I-605 reduced to one lane 9 p.m. Friday to 3 a.m. Saturday.

— Southbound I-605 reduced to two lanes from 3 a.m. Saturday to 4 a.m. Sunday.

— Southbound I-605 reduced to one lane from 4 a.m. Sunday to 8 a.m. Sunday.

— Southbound I-605 reduced to three lanes from 8 a.m. Sunday to 10 a.m. Sunday.

— All southbound I-605 lanes will reopen to the public by 10 a.m. Sunday.

Ramps:

— Southbound I-605 Peck Road off-ramp closed from 7 p.m. Friday to 10 a.m. Sunday.

— Eastbound SR-60 connector to southbound I-605 closed from 7 p.m. Friday to 10 a.m. Sunday.

— Westbound SR-60 connector to southbound I-605 closed from 8 p.m. Friday to 10 a.m. Sunday.

— Southbound I-605 connectors to eastbound and westbound SR-60 closed from 8 p.m. Friday to 10 a.m. Sunday.

The work is part of the Super 605 freeway corridor projects to rehabilitate the San Gabriel River (605) Freeway from Long Beach to the San Gabriel Valley.