The Foothill Gold Line Construction Authority Board of Directors has approved an updated workplan and schedule for the 12.3-mile, six- station Foothill Gold Line light rail extension from Glendora to Montclair, the board said Thursday.

The schedule assumes ground-breaking on the extension will begin in October and be completed in late-2025 to early-2026, based on detailed reviews completed late last year, authority CEO Habib F. Balian said.

“It is really two major projects in one – the freight and Metrolink relocation/reconstruction will have to be completed first, followed by construction of the light rail system,” he said.

The previously approved schedule, approved in 2015, had estimated completion in 2023.

—City News Service